Google datacentre in Belgium ordered to halt construction over missing permits

Belgian authorities have ordered Google to stop building a large datacentre at Aiseau-Presles, near Charleroi, after its request to modify the original planning permission was refused while the structure stood nearly finished.

By Haut Monde Post

• November 28, 2026

• 3 Min Read

Google datacentre in Belgium ordered to halt construction over missing permits

Inspectors find building nearly complete

Regional officials in Wallonia have served Google with a construction halt order for its large datacentre at Aiseau-Presles, after requests to change the original planning permission went unapproved. Wallonia regional official Raphaël Stokis said the site visit left little doubt about how far the project had gone.

"Inspectors visited the site and observed that the building was almost finished, with the structural work completed, even though the permit had been refused"

Stokis said the 300 workers on site received a verbal stop-work instruction, which was then confirmed in writing to Google.

The permit fight over water cooling

The dispute centres on how the facility, planned on a former coalmine site about 15km west of Charleroi, would be cooled:

  • •Google's 2024 permit covered three smaller air-cooled datacentres, of which the current building is one.
  • •In 2025 the company applied to combine two into a single larger building, cooled with water taken from the Sambre River at a rate of 600 cubic metres an hour.
  • •The regional administration signed off on those amendments in April 2025, but after appeals Wallonia infrastructure minister François Desquesnes withdrew the modified permit in August, citing drought concerns.

The building stands on about 3 hectares (7.4 acres) of a 50-hectare business park.

Prosecutors and Greenpeace enter the case

Regional government spokesperson Nicolas Yernaux told AFP on Friday that a report was being submitted to public prosecutors, alleging what he called "a major offence: the illegal construction of a building covering 3 hectares".

Greenpeace this week published drone footage showing Google carrying on construction work, and said in a report that "the tech giant is continuing work, even though in August the latest version of its planning permission to build this datacentre was revoked". The group filed an emergency appeal with local planning authorities, adding that "the climate crisis will only intensify in our region".

What happens next

Google said in a statement it was committed to maintaining an open and collaborative dialogue with the regional authorities. Against the withdrawal of its permit, Google has gone to Belgium's council of state; that body is due to rule on the matter on 7 January.

Google also faces separate scrutiny in Europe: Finland launched a criminal investigation in October into possible environmental law breaches at a planned datacentre in the rural north, and work there remains paused until environmental impact assessments are finished.

HAUT MONDE POST

Independent journalism of the highest standard. A chronicle of world culture, politics, arts, and public thought.

Publication

AboutEditorial

Newsletter

Get the best Haut Monde Post content delivered to your inbox every week.

© 2026 Haut Monde Post. All rights reserved. Digital edition hautmondepost.com.

Sunday, Nov 29, 2026

english

World

• Analysis

Google datacentre in Belgium ordered to halt construction over missing permits

Belgian authorities have ordered Google to stop building a large datacentre at Aiseau-Presles, near Charleroi, after its request to modify the original planning permission was refused while the structure stood nearly finished.

By Haut Monde Post

Nov 28, 2026 • 3 Min Read
Google datacentre in Belgium ordered to halt construction over missing permits

Inspectors find building nearly complete

Regional officials in Wallonia have served Google with a construction halt order for its large datacentre at Aiseau-Presles, after requests to change the original planning permission went unapproved. Wallonia regional official Raphaël Stokis said the site visit left little doubt about how far the project had gone.

"Inspectors visited the site and observed that the building was almost finished, with the structural work completed, even though the permit had been refused"

Stokis said the 300 workers on site received a verbal stop-work instruction, which was then confirmed in writing to Google.

The permit fight over water cooling

The dispute centres on how the facility, planned on a former coalmine site about 15km west of Charleroi, would be cooled:

  • •Google's 2024 permit covered three smaller air-cooled datacentres, of which the current building is one.
  • •In 2025 the company applied to combine two into a single larger building, cooled with water taken from the Sambre River at a rate of 600 cubic metres an hour.
  • •The regional administration signed off on those amendments in April 2025, but after appeals Wallonia infrastructure minister François Desquesnes withdrew the modified permit in August, citing drought concerns.

The building stands on about 3 hectares (7.4 acres) of a 50-hectare business park.

Prosecutors and Greenpeace enter the case

Regional government spokesperson Nicolas Yernaux told AFP on Friday that a report was being submitted to public prosecutors, alleging what he called "a major offence: the illegal construction of a building covering 3 hectares".

Greenpeace this week published drone footage showing Google carrying on construction work, and said in a report that "the tech giant is continuing work, even though in August the latest version of its planning permission to build this datacentre was revoked". The group filed an emergency appeal with local planning authorities, adding that "the climate crisis will only intensify in our region".

What happens next

Google said in a statement it was committed to maintaining an open and collaborative dialogue with the regional authorities. Against the withdrawal of its permit, Google has gone to Belgium's council of state; that body is due to rule on the matter on 7 January.

Google also faces separate scrutiny in Europe: Finland launched a criminal investigation in October into possible environmental law breaches at a planned datacentre in the rural north, and work there remains paused until environmental impact assessments are finished.

HAUT MONDE POST

Independent journalism of the highest standard. A chronicle of world culture, politics, arts, and public thought. Published and printed daily in Paris, France.

Publication

AboutEditorial

Newsletter

Get the best Haut Monde Post content delivered to your inbox every week.

© 2026 Haut Monde Post. All rights reserved. Digital edition hautmondepost.com. Published in Paris.

Sunday, Nov 29, 2026

english

World

• Analysis

Google datacentre in Belgium ordered to halt construction over missing permits

Belgian authorities have ordered Google to stop building a large datacentre at Aiseau-Presles, near Charleroi, after its request to modify the original planning permission was refused while the structure stood nearly finished.

By Haut Monde Post

Google datacentre in Belgium ordered to halt construction over missing permits

Inspectors find building nearly complete

Regional officials in Wallonia have served Google with a construction halt order for its large datacentre at Aiseau-Presles, after requests to change the original planning permission went unapproved. Wallonia regional official Raphaël Stokis said the site visit left little doubt about how far the project had gone.

"Inspectors visited the site and observed that the building was almost finished, with the structural work completed, even though the permit had been refused"

Stokis said the 300 workers on site received a verbal stop-work instruction, which was then confirmed in writing to Google.

The permit fight over water cooling

The dispute centres on how the facility, planned on a former coalmine site about 15km west of Charleroi, would be cooled:

  • •Google's 2024 permit covered three smaller air-cooled datacentres, of which the current building is one.
  • •In 2025 the company applied to combine two into a single larger building, cooled with water taken from the Sambre River at a rate of 600 cubic metres an hour.
  • •The regional administration signed off on those amendments in April 2025, but after appeals Wallonia infrastructure minister François Desquesnes withdrew the modified permit in August, citing drought concerns.

The building stands on about 3 hectares (7.4 acres) of a 50-hectare business park.

Prosecutors and Greenpeace enter the case

Regional government spokesperson Nicolas Yernaux told AFP on Friday that a report was being submitted to public prosecutors, alleging what he called "a major offence: the illegal construction of a building covering 3 hectares".

Greenpeace this week published drone footage showing Google carrying on construction work, and said in a report that "the tech giant is continuing work, even though in August the latest version of its planning permission to build this datacentre was revoked". The group filed an emergency appeal with local planning authorities, adding that "the climate crisis will only intensify in our region".

What happens next

Google said in a statement it was committed to maintaining an open and collaborative dialogue with the regional authorities. Against the withdrawal of its permit, Google has gone to Belgium's council of state; that body is due to rule on the matter on 7 January.

Google also faces separate scrutiny in Europe: Finland launched a criminal investigation in October into possible environmental law breaches at a planned datacentre in the rural north, and work there remains paused until environmental impact assessments are finished.